Search

SA poo plant undergoes historic upgrade

We are an online community created around a smart and easy to access information hub which is focused on providing proven global and local insights about sustainability

26 Feb, 2024

This post was originally published on Sustainability Matters

SA Water has just completed the single largest concrete pour at South Australia’s Bolivar Wastewater Treatment Plant — part of a $64 million upgrade that will create a new inlet structure at the facility.

More than 310 cubic metres of concrete was poured into the steel-lined base to create the inlet’s foundation, involving the coordination of around 50 mixing trucks across the complex 15-hour pour.

Bolivar’s new inlet is being built to increase the plant’s capacity to receive and process higher projected flow rates of sewage as Adelaide’s population grows.

SA Water’s Senior Manager of Capital Delivery, Peter Seltsikas, said along with the slab pour, the project has achieved a number of other milestones, including delivery of new screens that will be retrofitted on the inlet and act as the plant’s first line of defence, capturing and removing inorganic material.

“We’ve also recently started replacing three of our existing inlet pipes — which transfer raw sewage from across metropolitan Adelaide to the plant — while they remain temporarily connected to the existing inlet structure,” Seltsikas said.

Bolivar’s capacity to receive sewage from the network will more than double to about 630 million litres per day once the new inlet is operational.

A 20-tonne tower crane was deployed next to the inlet’s concrete slab to help crews lift equipment and pipes into place, along with large panels to facilitate concrete form work.

“Once the new inlet is complete, we’ll change the connections over and construct an additional three inlet pipes to accommodate increased flows that will come into the plant as the local population grows,” Seltsikas said.

“Despite ticking off the project’s single largest concrete pour, we anticipate we’ll need a further 1990 cubic metres, with our team now working on forming the concrete roof structure, overflow channels and walls.”

Seltsikas said SA Water hoped to begin installing the inlet’s mechanical equipment in the next few months. This process will involve eight customised screens, major support steel structure and ancillary items such as penstocks and stoplogs that control and isolate the flow of sewage.

To accommodate future projected flows, Bolivar’s capacity to receive sewage from the network will more than double to around 630 million litres per day once the new inlet is operational.

Top image caption: More than 310 cubic metres of concrete was poured into the steel-lined base to create the inlet’s foundation across the 15-hour operation.

Pass over the stars to rate this post. Your opinion is always welcome.
[Total: 0 Average: 0]

You may also like…

Government consulting on sustainable investment labelling

Government consulting on sustainable investment labelling

The Australian Government is starting consultation on sustainable investment product labelling, which is designed to give investors more confidence to put more capital to work in sustainable products.

The federal government said the release of this paper is a key step in implementing its Sustainable Finance Roadmap — designed to help mobilise the capital required for Australia to become a renewable energy superpower, modernising the financial markets and maximising the economic opportunities from net zero.

This consultation paper seeks views from investors, companies and the broader community on a framework for sustainable investment product labels.

These labels are designed to help investors and consumers identify, compare and make informed decisions about sustainable investment products to understand what ‘sustainable’, ‘green’ or similar words mean when they’re applied to financial products.

The government said a more robust and clear product-labelling framework will help investors and consumers invest in sustainable products with confidence and help tackle greenwashing.

This phase of consultation will run from 18 July to 29 August and help the government refine its design principles for the framework.

The consultation paper is available on the Treasury consultation hub.

Image credit: iStock.com/wenich-mit

0 Comments